Schedule
Schedule
gantt
tickInterval 4week
weekday monday
dateFormat YYYY-MM-DD
section Software
Software Architecture design :a1, 2024-01-13, 3d
Software Prototype Implementation :a2, after a1, 20d
Software Prototype Testing :a3, 2024-01-20, 20d
Software Implemantation and Testing of special Features :2024-02-10, 2024-08-01
section Hardware
Prototype Hardware Purchasing :b1, 2024-01-10, 5d
Prototype build :after b1, 24d
Prototype testing :2024-01-20, 24d
Hardware finalisation and testing :2024-02-22, 2024-04-01
section Management
writing Prototype Documentation :c1, 2024-01-18, 2024-02-22
Define Requirements :c2, 2024-01-08, 2024-01-13
section Phases*
Pitch :milestone, 2023-12-07
Engineering Phase :d1, 2023-12-07, 2024-01-13
Design Phase :d2, after d1, 3d
Requirements Verification : milestone, 2024-01-26
Implementation Phase :d3, after d2, 2024-02-12
Validation Phase :d4, after d3, 2024-02-22
working Prototype :milestone, 2024-02-22
Prototype Presentation :milestone, 2024-03-14
Product Release :milestone, 2024-08-14
*Phases according to PMBOK (Project Management Body of Knowledge)